CutterVic
Old and primitive, but solid for small businesses or subcontractors. To submit as the sub schedule to an enterprise scheduling software might take some work. This software is ancient. You will learn to schedule CPM and cost- and resource-loaded projects correctly with this product.
Does anyone know what might cause an independent or task activity to not accept a duration? I'm re-using a schedule and some of the activities have had their original duration taken to zero. I'm unable to enter any duration greater than zero for these activities. Activities with durations other than zero aren't affected.